Randle Reef - Hamilton, ON

Waterloo Barrier® Engineered Containment Facility

Completion Date: July 2018

Consultant: Riggs Engineering

Summary: 207,000 square feet of WEZ95 installed in the Hamilton harbour to isolate dredged contaminated lake sediments.

Features: The Waterloo Barrier® extended through 30 feet of water depth and 42 feet into the bottom of the harbour. Installation of the walls was completed in 2018, however other remediation activities are still ongoing.

Full Case History: Coming Soon