Former Gas Station - Newmarket, Ontario


Deep Complex Excavation Using Waterloo Barrier® Sheets

Completion Date: January 2011

Consultant: Pinchin

Summary: 1,650 square feet of WEZ95 cutoff wall was installed to intersect impacted groundwater from migrating into an adjacent river.

Features: The Waterloo Barrier® cutoff wall was designed as a temporary shoring system to facilitate the removal of impacted soil along the river bank.

Full Case History: Coming Soon